Case
Mobile Cranes
Cranes
Telecom

Hoisting of a telecom mast

Hoisting of a mast on a site with very limited space in a small protected forest in Højbjerg, where tree felling was not permitted.

A 48-meter mast, divided into four 12-meter sections, arrived on three trucks with steerable trailers, which had to navigate the narrow forest road.

The sections were assembled "in the air" one at a time, as there was no space to assemble them all on the ground.