Menu ikon

Contact local department

phone
Kraner på jackup-platform under arbejde på havvindmølle nær Samsø

Replacing drivetrains on five offshore wind turbines near Samsø

The drivetrains of five 2.3 MW offshore wind turbines near Samsø needed replacing. The offshore work required a stable working platform and the handling of components weighing up to 54 tonnes.

A 650-tonne mobile crane operated from a jack-up platform, while a 130-tonne auxiliary crane on a barge helped handle the heavy components. The jack-up platform’s four legs were lowered onto the seabed to provide a stable base at each turbine.

At each turbine, the rotor, weighing approximately 54 tonnes, was first removed and placed on a support on the barge. The drivetrain, consisting of the main shaft and gearbox and weighing around 40 tonnes in total, was then lowered.

After replacement, the components were lifted back into position.

When wind and other conditions allow, the work on one turbine can be completed in around 10 hours. For Per, Søren, Kaj and Morten, this was their fifth offshore assignment of this type and their second at the turbines near Samsø.

Meet Per, one of the crane operators behind the job, and read about his everyday work with heavy lifts.